The programme for delivery for Monifieth Learning Campus has been carefully considered to ensure the targets of the Learning Estate Investment Programme can be fully delivered.
These changes have extended the design stages of the project programme.
The delivery of the project will involve the construction of the building on the existing playing fields, allowing the existing building to continue to operate during the construction.
The target opening of the new build Monifieth Learning Campus is Summer 2025. The demolition of the existing building and the formation of external spaces is expected to be completed by Summer 2026.
Activity | Date from |
---|
Feasibility and Consultation | March 2021 |
Outline Design | November 2021 |
Engagement | July 2022 |
Detail Design and Tender | August 2022 |
Contract Award | May 2023 |
Construction Phase | June 2023 |
Decant | July 2025 |
Construction Phase 2 | September 2025 |
Project Complete | August 2026 |